SEBU7494-06 75
Operation Section
Operation
g01020535
Illustration 62
14. Install the position lock pin through the hole in the
material handling arm and the hole in the loader
arm of the machine.
15. Secure the load to the tie-down points with a
suitable line in order to minimize load swing.
Note: Do not move the load when you are securing
the load. Do not pull the load toward the material
handling arm when you are securing the load to the
tie-down points.
16. Remove the position lock pin and place the pin in
the STORED position on the material handling
arm.
Removing a Load
1. Fully tilt back the material handling arm. Fully
lower the loader arms.
2. Stop the engine. Exit the machine.
3. Install the position lock pin through the hole in the
loader arm of the machine.
4. Remove the line that secures the load t o the
tie-down points .
5. Remove the position lock pin and place the pin in
the STORED position on the material handling
arm.
6. Keep all personnel out of the work area.
7. Enter the machine. Start the engine.
8. Disengage the parking brake.
9. Lower the load t
o the ground.
10. Stop the engine. Exit the machine.
Note: Make sure that the load is stable.
11. Remove the loa
d from the hook.
12. Keep all personnel out of the work area.
13. Enter the machine. Start the engine.
14. Disengage the
parking brake.
15. Slowly tilt back the material handling arm until the
material hand
ling arm is fully tilted back.
16. Back away from the load.
TravelingwithaLoad
1. Ensure that al
l personnel have left the work area.
2. Start the engine.
3. Disengage the parking brake.
4. Raise the load
so that the load is slightly off of the
ground.
5. Slowly travel
to the destination. Keep the load as
close to the ground as possible. Travel up slopes
with the load uphill. Travel down slopes with the
load uphill.
Do not travel across slopes.
i01878348
Pallet Forks Operation
SMCS Code: 6700; 7000
g0095593
7
Illustration 63
The “type 1” pin that is in the unlocked pos ition (2) and the locked
position (1).